Specifically, the first wind power plant is Alpha VNM, invested in the communes of Ea Sol, Le De Yang and Ea Hiao (Ea Hleo district), with an area of nearly 6.5 hectares, capacity of 20 MW and total investment. 650 billion VND.
The second wind power plant is Beta, invested in the wards of Dat Hieu, An Binh, Doan Ket, Thong Nhat, Binh Tan and Cu Bao commune (Buon Ho town), Ea Ngai commune (Krong Buk district) and Ea commune. Tul (Cu Mgar district), area 10.9 ha, capacity of 50 MW, total investment 1,560 billion.
The implementation progress of these two projects is 24 months from the time of issuing the decision on investment policy, the operation period of 50 years. Representatives of the Peoples Committee of Dak Lak province said that these projects will enjoy preferential treatment for land rent, corporate income tax, and import tax according to regulations.
Dak Lak Provincial Peoples Committee requires project investors to be responsible for the legality and accuracy of information, data, content in project proposals, complete procedures for environmental protection, land as well as related procedures before project implementation and project implementation in accordance with the approved regulations, progress ...
Recently, at the end of December 2020, the Peoples Committee of Dak Lak province also agreed to the policy of Hoang Son Energy Investment, Construction and Trading Joint Stock Company to study and survey wind measurement to set up wind power projects in the district. Ea Hleo, Krong Buk and Krong Nang.
Specifically, in Ea Hiao commune (Ea Hleo district) and Cu Klong commune (Krong Nang district), Hoang Son enterprise surveyed and measured wind on an area of 2,735 ha, set up a wind power project with an expected capacity of 180MW. . In Ea Sol commune (Ea Hleo district), Hoang Son surveyed wind measurement with an area of 6,350ha, plant scale 500MW. In Cu A Mung commune (Ea Hleo district), the wind measurement enterprise has an area of 4,794ha and the plant scale is 150 MW. In Cu Kbo commune (Krong Buk district) and Ea Ho commune (Krong Nang district), the enterprise measured wind on an area of 2,602.4 ha, with a plant scale of 100MW.
In October 2020, the Peoples Committee of Dak Lak province also agreed to the policy for Hoang Son Company to have been surveyed, studied and prepared for a project proposal for a solar power plant project on Ea Sup Ha Lake, Ea Sup district.
Accordingly, investors will survey on an area of 120ha, of which 118ha of water surface, 2ha of land in the territory of Cu Mlan commune and Ea Sup town. This area has no natural forest, does not affect security and defense and does not overlap with other projects.