Geology condition

- Land height: 2.1m
- Compressive strength: 0.082 cm2/kg
- Cohesion strength C: 0.18 kg/cm2
- Natural unit weight: 1.96 g/cm3
- Compressibility coefficient: 1.74 kg/cm2

 

Roads
Main road system

+ Width: 40 m

+ Number of lanes: 4 lanes

- Road system: Provincial road No. 832 with the approximate width of 68.5 meters including 01 main road in the center (15 meters in width), and 02 double lines with the width of 7.5 meters, having the barrier with the width of 8.5 meters and sidewalk (2 sides) with the width of 7 meters.
- Waterway system: Vam Co Dong river system is one of the main waterway traffic systems in the key economic region of Southern Vietnam, and landing stage and warehouse are scheduled building along Vam Co Dong River with the length of quay about 500 meters

Internal road system

+ Width: 20 m

+ Number of lanes: 2 lanes

- Internal road system in Industrial zone is classified logically with 02 main roads 45.25 meters & 50 meters widen. Inside road system has the width of 39.5 meters & 45.25 meters, established with the demand of industrial standards about safety and effectively, such as: fire prevention and protection; emergency medical caring work; cargo and passengers transportation of each factory.

Power supply
The National grid

+ PoWer line: 22kv

- The electrical system belongs to the national electrical grid, supplied by an electrical medium voltage resource (voltage of 22 KV) connecting from 110KV power station at Ben Luc (double electrical circuit). This source will supply electricity to each factory in Nhut Chanh IP through an electrical cable system.

Standby power plant

+ N/A

Water supply

- Water supplying system of Nhut Chanh IP is supplied by Long An Water Supplying Factory.

- Drainage of rainfall and dirty water are separated
- Park system is planned for the whole in order to provide fresh air, prevent air pollution and create beautiful sights and comfortable working environment for the work force

Sewage treatment plant

+ 4,000 m3/day

- Waste water from factories is collected through the underground piping network and treated in the Sewage Treatment Plant with its capacity 4,000 m3/day in conformity to The Vietnam Environmental Standard before its falling into Vam Co Dong River. The wastewater shall be treated to meet The Vietnam Environmental Standard.

Internet

+ ADSL

Telecommunication

- Establishing the modern and international standard network of Postal & Telecommunication Service; such as to equip and install MDF, telephone system and ADSL provided by a Telecommunication Service and meet all demands of investors.

Homepage | News | Search | Comparison| Terms Of Use | Contact