Infrastructure
Geology condition

- High above sea level : about 2.7 m.

- Average humidity : 70% - 85%.

- Average temperature : 29-32 0 C,

- Average annual rainfall : 1,606mm

Roads
Main road system

- Main road D3, length 1,443.14m, cross-section 63m, lane for cars 24m, separator 3m.

- Main road N6, length 1,410m, cross-section 31m, lane for cars 15m.

- Others are 02 lanes, width 8m.

Internal road system

- Road 965 at the East-Southern, through PM2IZ, length 2,065m, planning cross-section 75m.

- Inter-port road at the West of PM2IZ, cross-section 50m.

Power supply
The National grid

Substation with capacity is 110/22kv - 103MVA supplying chiefly power to production factories in industrial zone.

Standby power plant

+ N/A

Water supply

From Phu My underground water plant with capacity of 20,000 m3 per day; assure to supply cleaned water to the fence of factories continuously 24hours/day.

Sewage treatment plant

+ Capacity in the 1st stage: 4.000m3/day

Internet

+ ADSL

Telecommunication

Sufficient telecommunication network assuring the convenient telecomunication in domestic and international calls.

Homepage | News | Search | Comparison| Terms Of Use | Contact

INDOCHINA INTERNATIONAL CONSULTING CO., LTD
KK11 Ba Vi Street, Ward 15, District 10 ,Ho Chi Minh City
®Source: http://viipip.com should be clearly quoted for any use of information extracted from our website.