Investment Procedure
Land
Leasing Price
1357525 VND, approximately: 65 USD/ m2/ 50 years
Leasing term
30/12/2055
Payment method
- Infrastructure maintain fee: 0.5 USD/m2/ year;
Pay two installments: at the 1st month and the
13th month since the date signing Contract.
Pay two installments: at the 1st month and the
13th month since the date signing Contract.
Minimum plot area
2ha
Factory
Leasing Price
0 USD/ m2/ month
Leasing term
+ N/A
Payment method
+ N/A
Scale of Factory
+ N/A
Deposit
+ N/A
Factory for sale
0 USD
Others
+ N/A
Management fee
Fee
0.200000002980232 USD/ m2/ month
Payment method
Electricity Price
Peak time
2049 VND/ KWH
Normal hour
1128 VND/ KWH
Off peak time
710 VND/ KWH
Other information
+ Charged by EVN
+ Excluding VAT/ KWH
Payment method
+ Monthly
Price of Water Supply
Price of Industrial water supply (m3)
7500 VND
Other information
+ Charged by Gov. suppliers
+ Not including VAT
Payment method
+ Monthly
Sewage Fee
Sewage Fee (m3)
0.319999992847443 USD
Method of counting the volume
+ Equal to 80 percent quanlity of clean water
Reference as: 0.32 USD
Payment method
+ N/A
Standard of input treatment
Level B
Standard of output treatment
QCVN 24: 2009/BTNMT
Other fee