Geology condition

The land will be provided at altitude of 1.85m and the designed altitude for construction is 2.2m.The flooding altitude in Long An is 1.45m with probability ratio of 1%. So, the land is currently 0.45m above the 100 year flooding level after filling-up the land.
Soil Bearing Pressure: <0,7 kg/cm2

Roads
Main road system

- Inter-road network including 2 main roads:

   + Road N4: 36 m (alongside South border of Industrial Park)

   + Road D1: 32m (alongside the West border of Industrial Park)

   + Road-lane: 4

- Xuyen A Road (Highway 22)

– North of Industrial Park.

- Border road 4 (DT823 – 824 – 825) towards to Tan An City and Ben Luc District.

- Border road 3- East of Industrial Park.

- Sea way located at Industrial Park: Thay Cai channel of 40m width capable of transporting small boats

Internal road system

- Internal roads

  + Width: 18-42 m

  + Road-lane: 2- 4

Power supply
The National grid

Electricity Company and currently promoting 110Kv power line for DUC HOA III - RESCO IP.
▪ 1 current local grid of 22 kV, capacity 40+63MVA, by Long An Electricity Company (EVN’s affiliate)
▪ 1 national grid of 110 kV, by Trang Bang – Duc Hoa power line which will be operated end of 2012. In 2013, DARESCO is going to build a transformer 110/22kV, capacity 1x25+1x40MVA

Standby power plant

+ Note:

The 3 peak months in 2011 were May, June and July due to the drought which caused lack of electricity for the whole country. In these 3 months, there were 3 scheduled shut down days but for maintaining the power supply system only.
The electricity is supplied with priority for DUC HOA III - RESCO IP. Most of the time the electricity were shut down in schedule, only with the unexpected problem, the electricity was shut down without notification. In the peak 3 months in 2012, there were no black out day.

Water supply

o From Phu My Vinh Long An Water Supply JSC, capacity 15.000m3/day & night

o From Kenh Dong Long An Water Treatment Plant, capacity of first period is 40.000m3/day & night.
The sustainable pressure for water is 2.5 – 3kg/cm2.
Restriction on water consumption: The water can be consumed in the whole year. There is no restriction on water consumption

Sewage treatment plant

Design capacity: 10.000 m3/day
The requirement to have a waste water treatment on site is depended on the quality of wastewater. The customer’s discharged waste water is required to meet level B of Vietnam waste water treatment standards and then level B waste water will be discharged to DUC HOA III - RESCO IP waste water treatment plant to treat to level A waste water before discharging to the environment.
▪ If, the customer’s discharged waste water already meets level B of Vietnam waste water treatment standards; so, there is not required to have a waste water treatment plant on site.
▪ If, the customer’s discharged waste water dose not meet level B of Vietnam waste water treatment standards; so, there is required to have a waste water treatment plant on site.

Internet

ADSL

Telecommunication

• Communication system in Duc Hoa III – RESCO Industrial Park is allowed to connect to Long An Telecommunication network.
• Its local system will be a telephone cable network with estimated subscription of 2,223, meeting sufficient requirements on telecommunication service in the industrial park.

Homepage | News | Search | Comparison| Terms Of Use | Contact

INDOCHINA INTERNATIONAL CONSULTING CO., LTD
KK11 Ba Vi Street, Ward 15, District 10 ,Ho Chi Minh City
®Source: http://viipip.com should be clearly quoted for any use of information extracted from our website.