Set as Homepage    Add Favorites

Construction of Thai Binh power plant set to begin
Date: 2/24/2014 9:43:04 AM
he construction of Thai Binh thermal power plant began on Saturday, with a combined design capacity of 600MW and an annual electricity production of 3.6 billion KWh.

 The plant is being built in My Loc Commune of Thai Thuy District in the northern province of Thai Binh by the Electricity of Viet Nam Group (EVN) and Japanese contractor Marubeni at a cost of VND26.5 trillion (US$ 1.27 billion).

The Japan International Co-operation Agency provided some 85 per cent of the capital through ODA and the remainder of the money came from the EVN.

The 115- hectare plant consists of two turbines. The first turbine is scheduled to begin generating power in November 2017, and the second in May 2018.

Speaking at the ground-breaking ceremony, Deputy Prime Minister Hoang Trung Hai asked the EVN to work closely with contractors to carry out the project in accordance with regulations on investment and construction.

Hai also requested local authorities to pay closer attention to the resettlement of displaced residents and inspections of the project’s progress.

(Source:VNN)
   Other news
Homepage | News | Search | Comparison| Terms Of Use | Contact | User

INDOCHINA INTERNATIONAL CONSULTING CO., LTD
HO Add: 62L/36 Nguyên Hồng, Ward 11, Bình Thạnh District, HCMC - Vietnam
Biz Office Add: #48 Road No 11, Quarter 6, Hiệp Binh Chánh Ward, Thủ Đức, HCMC - Vietnam
®Source: http://viipip.com should be clearly quoted for any use of information extracted from our website.
Publication permit No: 60/GP-TTĐT , April 05, 2010.